Objective
Design and manufacture a SALUS CONTROL panel. Critical lead time for this project: 60 days T0. 90 days mass production, Project done.
Research and Development
Mold Manufacturing
Injection Molding
Foil Film Research and Development
Material Inspection
Product Improvement
09/2020
Dongguan China
Started to work on the SALUS controls
10/2020
Dongguan, China
Mold Finished, T0 trial and test manufacture.
12/2020
Finished all tesing, start mass production