Objective
Design and manufacture a complex 2K Cover. Critical lead time for this project: 40 days T0. 120 days mass production, Project done.
Research and Development
Mold Manufacturing
Injection Molding
Foil Film Research and Development
Material Inspection
Product Improvement
02/2021
Qingdao & Dongguan, China
We started to work on the Haier Water Heater. This product is a virtual reality device made by Haier.
04/2021
Product launch.
We successfully finalised this project on time.
08/2021
Started developing derivatives of TRU1 and successfully launch in September.