IMR case-Haier Water heaters

Objective

Design and manufacture a complex faceplate for the S3 &P3 . Critical lead time for this project: 40 days. Project done. S3 &P3

Job Tasks

28

Research and Development

17

Mold Manufacturing

10

Injection Molding

30

Foil Film Research and Development

10

Material Inspection

5

Product Improvement

Review the Overview

 

11/2019

Qingdao&Dongguan, China

In September, it began to enter the mold making process


06/2020

Qingdao&Dongguan, China

We started to work on the Haier Water Heater. This product is a virtual reality device made by Haier.

08/2020

Product launch. We successfully finalised this project on time.


Website: https://www.haier.com/

The product won the red dot award 2022