Job Tasks

15

Research and Development

20

Mold Manufacturing

20

Injection Molding

15

Foil Film Research and Development

5

Material Inspection

7

Product Improvement

Review the Overview

03/2020  

Suzhou & Dongguan, China

In March, it began to enter the mold making process


04/2020

China

We successfully finalised this project on time.


05/2020

China

This batch of 7000 sets has been successfully completed, and all the products have been put into European and American markets